175
Woodview
Castletown
Celbridge
Co.
Kildare
24th
November 2005
Mr. Martin Cullen, TD.,
Minister for Transport
Department of Transport
Kildare Street
Dublin 2
RE: KILDARE ROUTE PROJECT (KRP)
- OBJECTION TO GRANTING OF RAILWAY ORDER
Dear Minister,
I
wish to object to the granting of a railway order to Irish Rail for the above
project on the grounds that the project is unnecessary and the desired increase
in capacity can be achieved by a change in station design and installation of a
proper signalling system. To launch such a project in the same week that the
HSE PPARS debacle was made public shows breathtaking arrogance on the part of
Irish Rail.
Irish Rail, in their publicity for this project,
has stated that the upgrade is to allow for the running of additional services.
I would contend that they have either understated the ability of the current
network to cope with additional services and/or have not considered other, more
cost effective options. To eliminate the first point (capacity of current
network), let me relate my experience of
travelling from Heuston
Station, Dublin to Hazelhatch & Celbridge Station on 27th
October 2005.
The 1800 service to Portlaoise was delayed,
departing Heuston Station at 1807. The 1755 to Galway (also delayed) departed
at 1811, i.e., only 4 minutes after the train before it. Between Heuston
Station and Inchicore, there are three tracks. At the time that the 1755
approached Inchicore, there was an empty train on one of these three lines and
a light engine (engine with no train) on another (the third was obviously
occupied by the 1755). What this means is that the 1800 was still ahead of the
1755 at this stage and not that the 1755 had overtaken it (which would have
eliminated the situation I am about to describe to you). With another train 4-5
minutes ahead of it, you would expect the 1755 to be delayed by red/orange
signals as it headed on its journey, if you believed Irish Rail's claims about
the lack of capacity on the Cork Line. For the record (and I am willing to
stand over this in court), between Heuston and Hazelhatch, only 1 signal was
orange when approached by the 1755, turning to green just before passing it and
another was what is known as double orange. This means that despite the close
proximity of trains, there was always at least one signal section ahead free
between the two trains with only a five minute headway between them. This would
suggest that Irish Rail do not need two additional tracks, just an updated
signalling system that would guarantee the ability to operate this way 24/7 if
required.
Irish Rail, if presented with this reality, would
claim that this worked only because neither the 1800 to Portlaoise nor the 1755
to Galway were required to stop at any intermediate stations between Heuston
and Hazelhatch and I don't disagree with this. However, the answer is not the
extravagant 4 track proposal being presented here.
The
KRP is proposing new stations at Park West, Fonthill, Kishoge and Adamstown,
the extensive remodelling of Hazelhatch along with the closure of Cherry
Orchard and Clondalkin. The latter two stations will be required to be
demolished, solely to accommodate the third and fourth tracks. In the case of
Clondalkin, Irish Rail have claimed that "this balanced judgement reflects
the exceptional case category for the demolition of protected structures as
contained in the Local Government (Planning & Development) Act 1999 as well
as the provisions for works a part of a Railway Order under the Transport
(Railway Infrastructure) Act 2001." I disagree that this is a balanced
judgement, as no consideration has been given to alternatives other than the complete
4 tracking of the line between Le Fanu Road and Hazelhatch being proposed here.
A
similar mentality exists with regard to the 11 overbridges also proposed for
demolition as well as the approach ramps to a limekiln in Stacumny (also a protected
structure) and a private residence near Hazelhatch where I note from the EIS
that "The removal of the property at Hazelhatch will have a profound
negative impact to the owner. Compensation at full market value may be
available to the affected property owner under the compulsory purchase
code." Only “may” be available? If it is open season on property, can I
sequestrate your house Minister? Or maybe Charlie McCreevy's (maybe not, I have
been reliably informed by someone who has seen the relevant planning file that
the latter is in breach of planning law, something that I am sure that you are
aware of from your time as Minister for the Environment).
The
proposals contained herein would obviate the need for any demolition by doing
the following. I will deal with the existing and proposed structures as set out
in the order that they are encountered, traveling from Le Fanu Road to
Hazelhatch & Celbridge station.
Specific alternatives:
1. Close Cherry Orchard station and leave it as is. The
existing footbridge across the line can remain to serve the residents of the
area. Irish Rail's proposal for a new footbridge 90m west of the existing
structure is unnecessary in this scenario.
2. Park West Station. Move slightly to the west and build as a two
island platform station with a loop off the Down and Up running lines, fully
protected by headshunts at each end, thereby enabling commuter trains to pull
in and be locked in, preventing an overrun of the commuter train or a running
into the loop of an intercity train (Appendix A). Such a layout would also
allow mainline trains to stop (not provided for in Irish Rail's plan)
3. Cloverhill Road Overbridge. Leave as is.
4. Clondalkin Station. Close the station and sell the Up side of
the station for conversion to a residence, thereby avoiding the demolition of a
“designated heritage building”. The EIS even admits:
"The demolition of Clondalkin station
house, which is a designated heritage building, will result in a profound
negative impact on the station itself and a significant negative impact on the
architectural heritage of the attendant area."
Irish
Rail's final solution to the problem of protected structures cramping the
freedom of their engineers to waste taxpayers money can be left to one side.
The additional land proposed for occupation by the KRP to be used to provide a
footpath/cyclepath alongside the line from Clondalkin to the new station at
Fonthill.
5. Neilstown Road Overbridge to be left as is.
6. Fonthill Station. Move slightly to the east (to avoid the
possibility of the new station design being constrained by the width under the
modern overbridge) and build as a two island platform station with a loop off
the Down and Up running lines, fully protected by headshunts at each end,
thereby enabling commuter trains to pull in and be locked in, preventing an
overrun of the commuter train or a running into the loop of an intercity train
(Appendix A)
7. Lynch's Lane Overbridge to be left as is.
8. Kishoge Station. Move to the east of Lynch’s Lane OB (to avoid
the possibility of the new station design being constrained by the width under
the modern overbridge or the original stone overbridge) and build as a two
island platform station with a loop off the Down and Up running lines, fully
protected by headshunts at each end, thereby enabling commuter trains to pull
in and be locked in, preventing an overrun of the commuter train or a running
into the loop of an intercity train (Appendix A)
9. Hayden's Lane Overbridge to be left as is.
10. Newcastle Road. I understand that this is separately scheduled for
demolition, a project that is not part of the KRP.
11. Finnstown Farm Overbridge to be left as is.
12. Adamstown Station. Build as a two island platform station with a
loop off the Down and Up running lines, fully protected by headshunts at each
end, thereby enabling commuter trains to pull in and be locked in, preventing
an overrun of the commuter train or a running into the loop of an intercity
train (Appendix A)
13. Stacumny Bridge to be left as it is. This will also avoid damage
to the adjacent protected structure of the limekiln. The EIS notes that the
limekiln is unusual in design, yet IR are proposing to demolish part of it.
Irish Rail's “gesture” of stabilizing the rest of the structure can be done
with the savings made by not four tracking the line. Just as local authorities
can and do impose social conditions on developers in return for granting
planning permission, I am specifically calling for the conservation of this
unique structure to be carried out by IR as part of the alternative KRP
attached herein.
14. OB 23 (east of Hazelhatch) to be left as is.
15. Hazelhatch to be closed and replaced on the west side of the
Hazelhatch Road by a two island platform station with a loop off the Down and
Up running lines, fully protected by headshunts at each end, thereby enabling
commuter trains to pull in and be locked in, preventing an overrun of the
commuter train or a running into the loop of an intercity train. The existing
loop alongside the former cattle bank and associated land to be used for the Up
side island platform and loop. A turnback siding and platform to be provided on
the Down side, to the south of the Down island platform and loop.
16. Irish Rail's “gesture” of restoring the disused station building
at Hazelhatch (a protected structure) can be done with the savings made by not
four tracking the line. Just as local authorities can and do impose social
conditions on developers in return for granting planning permission, I am
specifically calling for the restoration of this protected structure to be
carried out by IR as part of the alternative KRP attached herein.
17. Metal footbridge at Hazelhatch, proposed for refurbishment and
retention, to be moved to the new station upon completion to span the mainline,
connecting the two island platforms.
18. Hazelhatch Road Overbridge (a protected structure) to be left as
is.
I
have included the necessary crossovers on the attached diagram at Hazelhatch.
To facilitate the best possible options for turning back trains at any of the
stations or allowing bypassing in the event of a train failure, facing and
trailing crossovers at both ends of each of the new stations should be
considered, providing for the maximum possible utilisation of the proposed
track layout.
General
Observations
1. Le Fanu Road on the plan is at 7.3 km on the maps accompanying the
EIS. 7.3 km from where? As this is a stand alone project, logic would suggest a
start point of 0km, or the equivalent of whatever mileage from Heuston Station
Le Fanu Road is.
2. There will be a two track bottleneck between Le Fanu Road and
Kylemore Road. This will reduce the four track arrangement to nothing more than
a holding pen for trains. Unless, of course, an inefficiency is being setup in
order to justify another project?
3. I am sure that Irish Rail will cite insurance reasons as to why
the old stations would need to be demolished if my plan for four track stations
was adopted. I can only use this opportunity to refer to the ARROW safety
problem, which I am aware of.
4. Claims about restrictions in working hours for
construction/demolition processes are facetious in light of problems during
construction by/on behalf of Irish Rail at East Wall Road & Drogheda.
Personal guarantees must be provided by each individual Board member of CIE/
Irish Rail, agreeing to personal financial penalties in the event of such
working hours limits being breached. Any other restriction is unenforceable,
even if there was an impetuous on the part of the relevant local authority to
do so.
5. No mention is made in the EIS of where records of demolished
structures will be retained. It is common knowledge that certain individuals
(myself included) are personae non grata in the eyes of CIE/Irish Rail and
therefore any records so created must be vested with an organisation with an
open access policy. Neither CIE/Irish Rail nor their accomplices in the Irish
Railway Records Society have such a policy, regardless of what they might
claim. I would compare my treatment at the hands of the aforementioned bodies
as akin to an organised hate campaign.
6. It was noted in the EIS that residents associations in Clondalkin
raised concerns about the retention of listed structures. It is quite clear
that Irish Rail is set on carrying out the personal agendas of its engineers
and any objection will be ruled invalid. This consultation process is therefore
a sham. I would compare this situation to the Kildare bypass, which we now know
is causing the springs that feed Pollardstown Fen to dry up. A secondary
negative effect of this is that Waterways Ireland are having to pump water from
the Liffey at Leinster Aquaduct to keep water levels in the Grand Canal intact.
The engineers got it wrong, just as they have in this case.
7. It is my opinion that failure of the State to provide equal
funding to opponents of the KRP is in breach of the Coughlan decision, which
required the State to fund information campaigns of both sides of any argument
and not just the State's argument.
8. Irish Rail have claimed that this project will allow for trains
running every 15 minutes. Clearly your civil servants responsible for
monitoring Irish Rail are incompetent if they cannot see that you do not need
four tracks for 4 commuter trains an hour along with a maximum of another 4
mainline trains. I refer to the incident on 27th October as backup
for refuting this claim (subsequently repeated by Barry Kenny, IR's Press &
PR manager). I also refer to a statement by Christy Stapleton of Irish Rail concerning
the Maynooth Line doubling project, carried out about 4 years ago. In the
Liffey Champion of 14th November, 1998, he was quoted as saying that
there would be trains every 30 minutes at off peak times on the Maynooth Line.
7 years on, the residents of West Dublin and North Kildare are still waiting.
Past experience suggests that Irish Rail does not deliver. They therefore do
not need this project.
9. The alternative proposed herein would obviate the need to demolish
road overbridges, thereby avoiding the extensive delays to road traffic caused
by the associated road closures. The day of the car is ending, Minister.
Replacing bridges because they are too narrow to allow for greater use of an
invention, the operation of which is likely to be severely restricted in the
next 20 years due to fuel shortages/environmental concerns, is pointless and
economically wasteful.
10. The current costing for this
project is €380 million. No doubt that by the time the project commences, like
the LUAS, this will have risen to €700m or €800m. Irish Rail have alluded to
this eventuality by stating that they will not know the exact cost until the
outcome of the public inquiry due to be held into the project, by which stage,
the Rubicon will have been crossed and the taxpayer will be committed (by the
civil service). As with working hours, personal guarantees must be provided by
each individual Board member of CIE/ Irish Rail, agreeing to personal financial
penalties in the event of this publicised figure of €380m being exceeded.
A
better use for any savings would be the provision of a second road bridge over
the Liffey in Celbridge, thereby eliminated the chronic traffic problems of
that town.
Yours
sincerely
Ewan
Duffy